Saturday, 6th September 2008

News from the Guernsey Press

States owed £400,000

0300481.jpgTHE States is owed £400,000 by Miller & Baird, the company which built St Sampson’s Marina, said Public Services minister Bill Bell.

The company had been claiming more than the original contract price. In a letter sent to States members updating them on the financial status of three outstanding capital project contracts, Deputy Bell gave the unexpected news.

‘With the final certificate now issued, I can confirm that we are in the unusual position where the contractor actually owes the States monies,’ he said.
‘Taking into account various issues such as prepayments made in the early stages of the contract, penalty payments for late completion, legal costs and the money due in respect of the contractor’s occupancy of the St Andrew’s reservoir industrial site, the States is owed in the region of £400,000.

‘Steps are now being taken to seek recovery of these monies.’

The marina had a contract value of £3,416,381. The total certified by the engineer was £4,090,656.

Miller & Baird’s claim, which was disputed by the States, was for £7,114,330.

It is expected to comment today.

Deputy Bell added that the marina was proving to be both popular and good value for money.

‘Income from the moorings in St Sampson’s has risen from £15,000 in 2004, the last year prior to the marina being completed, to £294,000 in 2007.’

Further berths were being created which would produce additional income.

But disputes over the two other projects remain unresolved.

Deputy Bell said that the original contract price for work on the New Jetty, approved by the States in November 2001, was £2,554,973, a figure subsequently revised upwards without setting a fixed price.

The then Advisory and Finance Committee was given authority to agree revised figures.

To date, contractor Balvac has been paid £4,256,963. In April 2007 it had lodged a claim for £27.3m.

‘The States’ legal and consultants fees to date amount to £3,679,036,’ said Deputy Bell.

‘A large part of this has been spent in defending the claim of the contractor, preparation for the States counterclaim in respect of remedial works and preparing for remediation and arbitration.’

Mediation is scheduled for the second week of July, with an arbitration hearing expected to start in January should mediation prove unsuccessful.

The States filed its defence and counterclaim to Balvac’s claim on 31 March.

‘In the meantime both parties, being acutely aware that as each month passes the significant legal costs of preparing for arbitration continue to mount, are using every effort to explore whether there is any cheaper resolution of the matter,’ said Deputy Bell.

He said that discussions were continuing which had allowed both sides to understand the other’s case more clearly and as a minimum ought to enable some issues to be resolved prior to arbitration.

No payments had been made since June 2005.

A spokeswoman for Balfour Beatty, Balvac’s parent company, said that as discussions were ongoing it was inappropriate to comment.

He could not say much about the dispute over the cost of the airport terminal because of the possibility of legal action by the States.

But his department had taken advice from the Law Officers and independent specialists and had written to the consulting engineers who were responsible for the mechanical and electrical design seeking compensation for losses arising from the delays the project suffered.

Have your say on  'States owed £400,000', comment below

Classifieds - 468
Whats On - 230Shopping - This is Guernsey
Car Finder - 468

4 Article Comments

  1. Stephen John

    Must be election time!!!

    Perhaps Bill Bell should reflect on why the company were allowed to get into the position where they were overpaid and what it says about the due diligence of his department.

    Doesn’t increase confidence one little bit.

  2. John

    Bill Bell’s comments are obviously premature, if the dispute with the contractor has not yet gone to arbitration which he says it hasn’t, how can he possibly now what the final cost is.

    It is arrogant to just dismiss the Contractor’s contractual claims in this way.

    He mentions penalty payments which will only become due when the arbitrator’s judgement is made, he mentions legal costs which again will be part of the judgement by the Arbitrator.

    The rental of States land at the St. Andrews reservoir is surely a seperate agreement which would not form part of the contract for the St. Sampsons Harbour.

    Sounds to me much like the wool is being pulled over the publics eyes yet again.

  3. Frances de Carteret

    If the states engineer had realised what everyone else knew already, that Guernsey is built on ROCK, there would not have been the necessity for the overspend. Why doesn’t anyone look into who provided erroneous advice upon which quotes were provided, in the first place?

  4. John

    The states KNOW what they have specified in the tender documents, so why do they argue when the actual conditions change from those specified initially.

    Lets face it the specifications were not right, the ground reports were not right.

    Why did we pay so much for consultants?

Post a Comment on this Article

Your email address is never published nor shared. Required fields are marked *

*
*

Disclaimer: We prefer short comments that include no external website links. Please ensure your comment is concise and relates to the article it accompanies. If it is irrelevant or deemed too long, it will not be approved. We reserve the right to edit or reject comments and will not enter into correspondence over editing decisions. Comments that appear on the site are not representative of the views of the This Is Guernsey or Guiton Group.

Your Shout: View all recent comments. More detail on the comment icons.

If you wish to make a comment about this website, please use our feedback form.